The problem
~150 projects steered through a monthly Excel report: 2 days of preparation, data out of date on release and no consolidated view. The real need: the right data at the moment of decision.
What discovery revealed
- Project slippage detected too late to correct.
- Trade-offs made without reliable, up-to-date data.
- No visibility for managers on their teams’ workload or cross-project requests.
- Unspent budget, invisible when trade-offs were made.
What I did
Discovery20 interviews at launch, then a cycle every quarter. 4 personas identified.
Vision“Give strategic and operational visibility over the IT project portfolio through a unified, scalable platform.” In practice: move from a monthly report to reliable data, refreshed daily.
Trade-offsAn MVP that first automates the existing report: new requests wait. Only the KPIs that drive decisions stay (Use Case, Cost, Impact / MoSCoW).
DataReliable data before the screen: 14 APIs connected and data-quality rules defined before development.
Prototype and deliveryWith no designer or QA on the team, I designed the flows and wireframes, tested prototypes with the 4 personas, then ran acceptance testing. MVP shipped in 4 months.
Rollout and measurementProgressive rollout, by user groups. Adoption tracked feature by feature, daily at each launch then as a monthly average, plus NPS. A second product, Data Quality, keeps the data reliable.
The cockpit
Four cockpit screens, reduced to their message. The real screens, I show them in interviews.
Redrawn excerpt · fictional data- Spent
- 7,100 d
- Planned
- 8,400 d
- Year-end projection
- 9,800 d
- Projects
- 29%
- Team activity
- 18%
- Day-to-day activity
- 53%
- Project A−260
- Project D−220
- Project H−140
- Project E−90
- Project B−60
- Project F+90
- Project C+120
- Project G+160
- Over 200 days behind
- Under 200 days behind
- On track
- Department B77%
- Department A92%
- Department C200%
- Department D208%
- Not enough people
- Spare capacity
Results
95%average feature adoption (target 80%)Monthly average per feature, across ~250 users
+55NPS180 respondents out of ~250 users (72%) · 60% promoters, 5% detractors
75%reporting preparation time saved2 days → 0.5 day per month, for the PMO team
Testimonial
“His work was decisive in turning a heavy, manual process into a real-time BI solution. […] Always available and proactive, he also brought stakeholders together around a coherent roadmap.”
What I took away
“Adoption is won during discovery, not at rollout.”How I work →